Supreme Court of India· 28 April 2023

2023 INSC 467

2023 INSC 467 · CIVIL APPEAL NO. 3151 OF 2023
Coram: Justice M.R. Shah · Justice C.T. Ravikumar
Full text of the Supreme Court of India's judgmentChecked against the originalFree to read
🔖 Save this judgment📬 Get today's judgments
View the original judgment PDFFree to read. To download it — or the LexStreak typeset copy with the headnote and Points of Law — create an account; downloads are part of the Pro plan.

One judgment a day. That's the whole habit.

LexStreak turns the Supreme Court's output into a five-minute daily read for advocates — plain-language headnotes, the questions each judgment settles, and the full text when you need it.

🔖Save judgments into folders you actually use
📚A daily feed curated to your practice areas
🔥A reading streak, and your place on the Bar leaderboard
Create my free account

Free forever plan · 30 seconds · data stays in India

Full judgment
1.

Feeling aggrieved and dissatisfied with the impugned judgment and order passed by the High Court of Delhi at New Delhi in Writ Petition (C) No. 4954 of 2016, by which, the High Court has allowed the said writ petition and has declared that the acquisition with respect to the land in question is deemed to have lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (hereinafter referred to as “Act, 2013”), the Govt. of NCT of Delhi has preferred the present appeal.

2.

Learned counsel appearing on behalf of the appellant(s) has submitted that in the present case the possession of the disputed land in question was taken on 31.12.2013 and therefore, as per the law laid-down by this Court in the case of Indore Development Authority Vs. Manoharlal and Ors., reported in (2020) 8 SCC 129 there shall not be any deemed lapse of acquisition under Section 24(2) of the Act, 2013.

2.1 On the other hand, learned counsel appearing on behalf of the original writ petitioner – respondent No. 1 herein has submitted that the actual/physical possession is with the original writ petitioner and only a paper possession was taken. It is submitted that even the possession is alleged to be taken on 31.12.2013 and before that the Act, 2013 has come into effect. It is submitted that it is rightly observed and held by the High Court that as neither the compensation was paid nor the possession was taken, there shall be deemed lapse of acquisition under Section 24(2) of the Act, 2013.

3.

Having gone through the impugned judgment and order passed by the High Court, it appears that it was the specific case on behalf of the appellants that the possession of the land in question was taken over on 31.12.2013. The Act, 2013 has come into force w.e.f. 01.01.2014. Therefore, the date on which the Act, 2013 came into force the possession was already taken over.

3.1 The submission on behalf of respondent No. 1 – original writ petitioner that only a paper possession was taken and actual/physical possession has not been taken is concerned, it is required to be noted that the possession of the land in question is taken over by drawing the punchnama which is held to be legal mode of taking the possession as per the decision of this Court in the case of Indore Development Authority (supra). Therefore, we have to proceed on the premise that the possession of land in question was taken over. Even the High Court has also proceeded further with the matter not disputing that the possession of the land in question was taken on 31.12.2013. However, thereafter, on the ground that no compensation has been paid/tendered to the original writ petitioner, thus, one of the two ingredients of Section 24(2) of the Act, 2013 is met, the High Court has declared that the acquisition with respect to the land in question is deemed to have lapsed. The aforesaid reasoning and the findings given by the High Court is just contrary to the law laid -down by this Court in the case of Indore Development Authority (supra). In the case of Indore Development Authority (supra), it is observed and held that for deemed lapse under Section 24(2) of the Act, 2013, twin conditions of not taking possession and not tendering/paying the compensation are required to be satisfied. Therefore, if one of the two ingredients of Section 24(2) of the Act, 2013 is not met, there shall not be any deemed lapse of acquisition under Section 24(2) of the Act, 2013.

4.

Applying the law laid down by this Court in the case of Indore Development Authority (supra) to the facts of the case on hand, the judgment and order passed by the High Court declaring that the acquisition with respect to the land in question is deemed to have lapsed is unsustainable and the same deserves to be quashed and set aside and is accordingly, quashed and set aside. Present appeal is accordingly allowed. No costs. Pending applications, if any, also stand disposed of. ………………………………….J. [M.R. SHAH] NEW DELHI; ………………………………….J. APRIL 28, 2023. [C.T. RAVIKUMAR]

What the Court decided this week

Can a plaint be rejected under Order VII Rule 11(d) CPC when limitation is a mixed question?

CIVIL APPEAL NO. 14807 OF 2024 · Supreme Court of India

Must stray dogs removed from schools and hospitals be released back to the same location?

2025 INSC 1357 · Supreme Court of India

Are the Motor Vehicle Aggregator Guidelines 2020 binding on a State Government issuing an aggregator licence?

2023 INSC 102 · Supreme Court of India

The Supreme Court decides something every day. Read one a day.

A free account gets you the day's judgments in your practice areas, a reading streak, and folders to keep what matters.

Start reading free
Source: Supreme Court of India. Reproduced for open access to public legal records, as issued — we add no masking of our own.
Headnote and questions prepared by the LexStreak Editorial Desk · Report an error · Privacy