LexStreak
Read free →
Civil — General
Supreme Court of India

In an interim order on a PIL challenging a PMGSY road-tender award, the Supreme Court extended three months for the appellant contractor to complete the remaining work at the rates prevailing on 15.03.2024, modified its interim order dated 07.03.2025 to that extent, and directed re-tender only if the work is not completed within the extended period; the appeal was deferred for a compliance report in December 2026.

O.P. MEHTA v. MOHINDER KALTA & ORS
2026 INSC 1037 · CIVIL APPEAL NO.12968 OF 2026 · 23 September 2026
Coram: Justice Dipankar Datta · Justice Sheel Nagu
Full text of the Supreme Court of India's judgmentChecked against the originalFree to read
🔖 Save this judgment📬 Get today's judgments
View the original judgment PDFFree to read. To download it — or the LexStreak typeset copy with the headnote and Points of Law — create an account; downloads are part of the Pro plan.
Headnotes

Public Interest Litigation — Tender validity — PMGSY road works — Interim order — Extended time — (Interim order)

Interim order — Extended time — PMGSY road work — Compliance —

Held: In view of the appellant's assurance to complete the remaining PMGSY road work without compromising quality, the Court extended time by three months at the rates prevailing on 15.03.2024, and modified its interim order dated 07.03.2025 to that extent, directing re-tender if the work is not completed within the extended period; listed for a compliance report in December 2026. (¶5, 5.1, 6, 8)

Points of Law
Result of the Judgment

What did the Supreme Court finally decide on the PMGSY road-tender appeal?

In view of the appellant's assurance to complete the remaining PMGSY road work without compromising quality, the Court extended three months at the rates prevailing on 15.03.2024, modified its interim order dated 07.03.2025 to that extent, and directed that the official respondents re-tender the work only if it is not completed within the extended period; the matter was listed for a compliance report in the first week of December 2026. (¶5, 5.1, 6, 8, 9) [5, 6, 8, 9]

Prepared by the LexStreak Editorial Desk — verify against the judgment.

Key passages from the judgment
Paragraph 1Jump →

“1. These appeals assail the Division Bench decision of the High Court of Himachal Pradesh, Shimla, rendered in a PIL bearing CWPIL No.30 of 2024 on 24.12.2024, whereby the PIL was allowed by quashing the award of work in favour of respondent No.5 therein (appellant herein) and directing the official respondents to re-tender the remaining work of upgradation of Matiana, Mahori to Chhaila road, Km. 0/00 to 25/650 under PMGSY package No. HP-09-694 within one month from the date of the judgment.”

Paragraph 4Jump →

“4. It cannot be overlooked that the petitioner before the High Court, as the alter ego of the unsuccessful bidder, filed the PIL questioning the tender process. The said unsuccessful bidder had complained against the successful bidder and has since withdrawn the complaint.”

Paragraph 6Jump →

“6. The instant case stands deferred to be listed in the first week of December, for the appellant to submit compliance report of this order.”

Paragraph 8Jump →

“8. That by order dated 07.03.2025, this Court had till the pendency of this appeal restrained the official respondents from creating third party rights, which interim order continues to subsist till date. Therefore, to the extent indicated above in this order, the said interim order dated 07.03.2025 stands modified.”

Headnote & Points of Law

You've used your free headnotes this month

The Court's judgment is below in full, free, as always — that never changes. What needs an account is LexStreak's own work on it: the headnote, the questions this judgment settles, and the passages that decide them. A free account opens all of it again.

Create my free account

Free forever plan · 30 seconds · data stays in India

Full judgment
1.

These appeals assail the Division Bench decision of the High Court of Himachal Pradesh, Shimla, rendered in a PIL bearing CWPIL No.30 of 2024 on 24.12.2024, whereby the PIL was allowed by quashing the award of work in favour of respondent No.5 therein (appellant herein) and directing the official respondents to re-tender the remaining work of upgradation of Matiana, Mahori to Chhaila road, Km. 0/00 to 25/650 under PMGSY package No. HP-09-694 within one month from the date of the judgment.

2.

The aspect which glares in the face in present case is as to whether the issue of validity of a tender, where comparative claims of competing tenderers are to be adjudged, can be raised as subject matter of challenge in a PIL?

2.1. We have our reservations since the grounds raised in the PIL before the High Court of Himachal Pradesh, Shimla pre-dominantly dealt with, inter-se comparative assessment between the two bidders whose bids had been received including respondent No.5 therein (appellant herein).

2.2. Moreso even the cost of work (Rs. 23 crores) was not of such magnitude, which may allow the petitioner in PIL to raise the plea of wastage of public resources.

3.

Certain factors which weighed in the mind of the High Court, for rendering the impugned judgment, were as follows: i. The contradictory stand taken by the official respondents as to whether the complaint made by M/s PK Construction Pvt. Ltd. (the other bidder) was actually received by the official respondents or not and if received then whether it was withdrawn or not. ii. Whether the experience gained by the appellant was as a sub-contractor or as a prime contractor. iii. Whether the appellant could have been allowed to operate under two different names in violation of certain clauses of the tender documents. iv. Though it was admitted in the impugned order that sub-contracts were allowed under the terms and conditions of the tender document but subject to fulfilment of certain conditions which were found missing in the instant case. v. The nature of work experience gained by appellant, as reflected from his work experience certificate was at variance to the nature of work actually executed in the past.

4.

It cannot be overlooked that the petitioner before the High Court, as the alter ego of the unsuccessful bidder, filed the PIL questioning the tender process. The said unsuccessful bidder had complained against the successful bidder and has since withdrawn the complaint.

5.

During the course of argument, we were informed vide affidavit of appellant dated 03.09.2026 that three (03) Kms. of road construction is complete along with retaining and breast walls of Matiana to Mohri Road in Distt-Shimla (H.P.) and that appellant is ready and willing to complete the work at the same rates on which the work was awarded to appellant on 15.03.2024. Appellant has assured that quality of work shall not be compromised.

5.1 In view of the aforesaid assurance made by the appellant, we extend a period of three months for the appellant to complete the entire work allotted to him on 15.03.2024 at the rates prevailing as on 15.03.2024. If the work so assigned to the appellant is not completed within the given time of three months subject to the official respondents verifying the quality of the work executed, the official respondents are directed to re-tender the same work at the prevailing market rate.

6.

The instant case stands deferred to be listed in the first week of December, for the appellant to submit compliance report of this order.

7.

This order shall also govern Civil Appeal No.12969 of 2026 preferred by the State of Himachal Pradesh.

8.

That by order dated 07.03.2025, this Court had till the pendency of this appeal restrained the official respondents from creating third party rights, which interim order continues to subsist till date. Therefore, to the extent indicated above in this order, the said interim order dated 07.03.2025 stands modified.

9.

List in the 1st week of December, 2026, for appellant to file compliance report. ……………………………...J. (DIPANKAR DATTA) …...………………………...J. (SHEEL NAGU) NEW DELHI; SEPTEMBER 23, 2026

What the Court decided this week

Is an employee's removal invalid under Article 311(1) where the removing authority is subordinate in rank to the appointing authority?

2026 INSC 1047 · Supreme Court of India

Can a remand for fresh trial on the Mandvi dictum be ordered where the accused never alleged prejudice?

2026 INSC 1053 · Supreme Court of India

Does a victim's appeal against a Magistrate's acquittal under the BNSS lie to the same court as an appeal from that Magistrate's conviction?

2026 INSC 1052 · Supreme Court of India

The Supreme Court and the Madras High Court decide something every day. Read one a day.

A free account gets you the day's judgments in your practice areas, a reading streak, and folders to keep what matters.

Start reading free

One judgment a day. That's the whole habit.

LexStreak turns the Supreme Court's and the Madras High Court's output into a five-minute daily read for advocates — plain-language headnotes, the questions each judgment settles, and the full text when you need it.

🔖Save judgments into folders you actually use
✍️Highlights and notes that follow you to every device
📚A daily feed curated to your practice areas
🔥A reading streak, and your place on the Bar leaderboard
Create my free account

Free forever plan · 30 seconds · data stays in India

Source: Supreme Court of India. Reproduced for open access to public legal records, as issued — we add no masking of our own.
Headnote and questions prepared by the LexStreak Editorial Desk · Report an error · Privacy