LexStreak
Read free →
Supreme Court of India· 22 September 2026

Does a clause barring interest on money lying due to a dispute and on delay in making payments bar the arbitrator's power to award pre-reference interest?

North Eastern Electric Power v. Astra Construction Private Limited
2026 INSC 1036 · SPECIAL LEAVE PETITION (CIVIL) NO. 24803 OF 2025
Coram: Justice Pamidighantam Sri Narasimha · Justice Alok Aradhe
🔖 Save this judgment🔔 Follow s.31(7)(a) Arbitration and Conci…📬 Get today's judgments
View the original judgment PDFFree to read. To download it — or the LexStreak typeset copy with the headnote and Points of Law — create an account; downloads are part of the Pro plan.
Answer

A clause barring interest on money lying due to a dispute and on delay in making payments bars the arbitrator's power to award pre-reference interest.

Yes. Where a clause bars interest both on money lying with a party owing to a dispute and, separately, on delay in making payments, it operates as a complete bar on the arbitral tribunal's power to award interest, whether pre-reference or pendente lite. Clause 54 of the GCC was held to be such a clause. (¶19, 20)

Headnote

Arbitration and Conciliation Act, 1996 — s.31(7)(a) — Pre-reference interest — Pendente lite interest — Contractual bar on interest — Arbitration and Conciliation Act, 1996 — s.31(7)(a) — Pre-reference interest — Substantive, not procedural — Held: Pendente lite interest stands on the footing of procedural law and is governed by section 31(7)(a) of the Arbitration and Conciliation Act, 1996. Interest for the pre-reference period stands on a different footing, being referable to substantive law, and cannot be sourced in section 31(7)(a) alone. (¶15) Contract clause barring interest — Two independent situations — Complete bar on arbitrator's power — Held further: A clause barring interest on money lying due to a dispute and, separately, on delay in making payments operates as a complete bar on the arbitral tribunal's power to award interest, whether pre-reference or pendente lite. Clause 54 of the GCC was such a clause, and the High Court's judgment restoring the award of pre-reference interest is set aside. (¶19, 20, 23)

Headnote

You've used your free headnotes this month

The answer above and the Court's own paragraphs stay free. LexStreak's full headnote on this judgment needs an account — a free one opens it again.

Create my free account
In the Court's own words
Paragraph 19Clause 54 of the GCC is worded differently, and the difference matters. It bars claims for interest or damages in two separate situations, not one. The first is the same as before, money or balance lying with the Corporation owing to a dispute, difference or misunderstanding. But Clause 54 then adds, in its own right and joined by the word "or", a second, independent situation, "any delay on the part of the Engineer-in-Charge making periodical or final payments", before finally adding the same closing words, "or in any other respect whatsoever." This is not a small drafting difference. By naming delay in payment as a separate ground, standing on its own and not tied to any dispute, Clause 54 does what the clause in Harish Chandra (supra) never did: it expressly shuts out a claim for interest arising from delayed payment, whether or not there was any dispute about it at all. The very situation that fell outside the bar in Harish Chandra (supra), delay in payment, without more, is brought squarely inside the bar in Clause 54. That is the true and complete answer to the High Court's view that the two clauses say the same thing; they do not, and the difference is decisive.
Paragraph 20This is also not a one-off or unusual way of drafting such a clause. The very same structure, a separate, additional line barring interest on delayed payments, over and above the bar on money withheld due to a dispute, appears in the clauses that this Court examined in Sayeed Ahmed (supra) and THDC-II (supra), and in each of those cases, for that very reason, this Court held that the clause was a complete bar on the arbitrator's power to award interest, whether for the pre-reference period or pendente lite. We respectfully agree with that reasoning and see no reason to depart from it. It follows that the High Court was in error in treating Clause 54 as no different from the clause in Harish Chandra (supra). The two clauses are worded differently, and that difference in wording makes all the difference in law. It is the line of decisions in Sayeed Ahmed (supra) and thereafter, not Harish Chandra (supra), that governs this case.
Acts & Sections
s.31(7)(a) Arbitration and Conciliation Act, 1996s.37 Arbitration and Conciliation Act, 1996

One judgment a day. That's the whole habit.

Read the full text of North Eastern Electric Power v. Astra Construction Private Limited — and get the Supreme Court's output as a five-minute daily read, with plain-language headnotes and the questions each judgment settles.

Create my free account

Free forever plan · 30 seconds · data stays in India

Open the full judgment →

Also decided in this judgment
Can interest for the pre-reference period be sourced in section 31(7)(a) of the Arbitration and Conciliation Act, 1996 alone?
Plain-language answer prepared by the LexStreak Editorial Desk — verify against the judgment. Source: Supreme Court of India. Corrections