Supreme Court of India· 12 August 2026

Under Section 3(12) of the Insolvency and Bankruptcy Code, 2016, does the mere subsistence of an EPC contract, whose obligations remain unfulfilled, provide the operational creditor a continuing cause of action that keeps its claim within limitation indefinitely?

SRINIVASA REDDY VELAGALA v. SRAVANTHI INFRATECH PVT. LTD
2026 INSC 835 · CIVIL APPEAL NO. 876 OF 2021
Coram: J. B. Pardiwala; Manoj Misra
🔖 Save this judgment🔔 Follow s.9 Insolvency and Bankruptcy Co…📬 Get today's judgments
View the original judgment PDFFree to read. To download it — or the LexStreak typeset copy with the headnote and Points of Law — create an account; downloads are part of the Pro plan.
Answer

No. Default under Section 3(12) occurs at a singular point in time when the debt becomes due and payable and is not paid, and an unpaid debt causing continuous damage does not amount to a continuing legal injury; the subsistence of the contract does not itself provide a continuing cause of action.

Headnote

Insolvency and Bankruptcy Code, 2016 — s.9 — s.3(12) — s.5(21) — Operational debt — Pre-existing dispute — Limitation — Effluxion of time — Frustration of contract — Indian Contract Act, 1872 — s.56 — Insolvency and Bankruptcy Code, 2016 — s.3(12) — "Default" — Continuing cause of action — Limitation Act, 1963 — s.18 — Acknowledgment — Held: Default under Section 3(12) occurs at a singular point in time when debt becomes due, payable and unpaid, not a continuing cause of action; absent acknowledgment under Section 18, Limitation Act, 1963, legal notices could not reset limitation, and the application was time-barred. (¶72, 82, 100) Insolvency and Bankruptcy Code, 2016 — s.9 — Effluxion of time — Frustration of contract — Self-induced frustration — Held further: Effluxion of time describes a contract's natural close, and frustration requires a supervening impossibility, not self-induced frustration arising from a party's own election; neither party having terminated it, the EPC contract continued to subsist. (¶40, 44, 47) Insolvency and Bankruptcy Code, 2016 — s.5(21) — Operational debt — Pre-existing dispute — Genuineness — Held further: Amounts under the EPC contract's payment schedule qualified as operational debt, though suspension and demobilization charges remained damages until assessed and crystallized by adjudication; the appellant's total, consistent silence across every legal notice showed no dispute that was spurious, hypothetical or illusory, so no pre-existing dispute barred the claim. (¶54, 60, 64, 93, 96) Insolvency and Bankruptcy Code, 2016 — s.9 — Appeal allowed — Liberty granted — Held further: The appeal was allowed and the NCLAT's and NCLT's orders admitting the Section 9 application were set aside; liberty was given to the respondent to approach the appropriate dispute resolution forum under the EPC contract to contest its claims. (¶101, 102)

In the Court's own words
Paragraph 72A default arising out of non-payment of the due and payable amount, provides cause of action on the date when the default occurs and cannot serve as a continuing cause of action. We say so because though an unpaid debt may cause continuous damage, yet it does not cause continuing legal injury. In other words, the legal default itself happens only once even though its consequences may be continuing in nature. Therefore, the respondent’s assertion that the subsistence of contract would provide it with continuing cause of action is incorrect and liable to be rejected.
Paragraph 73The “default” envisaged under Section 3(12) of the IBC occurs on non- payment of debt when whole or any part/instalment of the debt becomes due and payable but is not paid by the debtor. Thus, Section 3(12) grounds the occurrence of default at a singular point in time. The mere subsistence of the EPC contract will not give continuing cause of action in respect of the defaulted amount.
Acts & Sections
s.9 Insolvency and Bankruptcy Code, 2016s.5(21) Insolvency and Bankruptcy Code, 2016s.3(12) Insolvency and Bankruptcy Code, 2016s.8 Insolvency and Bankruptcy Code, 2016s.238A Insolvency and Bankruptcy Code, 2016s.56 Indian Contract Act, 1872Art.137 Limitation Act, 1963s.18 Limitation Act, 1963s.5 Limitation Act, 1963s.7 Insolvency and Bankruptcy Code, 2016

One judgment a day. That's the whole habit.

Read the full text of SRINIVASA REDDY VELAGALA v. SRAVANTHI INFRATECH PVT. LTD — and get the Supreme Court's output as a five-minute daily read, with plain-language headnotes and the questions each judgment settles.

Create my free account

Free forever plan · 30 seconds · data stays in India

Open the full judgment →

Also decided in this judgment
Can legal notices demanding payment, sent by an operational creditor without any written acknowledgment of liability by the corporate debtor, extend the period of limitation under Section 18 of the Limitation Act, 1963 for a Section 9 application under the Insolvency and Bankruptcy Code, 2016?Under the Insolvency and Bankruptcy Code, 2016, where an EPC contract remains suspended for non-payment but neither party invokes the termination clause, does the contract come to a natural close by effluxion of time, and can the suspension amount to frustration of the contract?Under Section 5(21) of the Insolvency and Bankruptcy Code, 2016, do suspension, idling and demobilization charges claimed by an operational creditor qualify as operational debt in a Section 9 application?Can a corporate debtor's total silence in response to an operational creditor's legal notices, followed by disputing the claim only after a Section 9 application is filed, still establish a pre-existing dispute under the Insolvency and Bankruptcy Code, 2016?
Plain-language answer prepared by the LexStreak Editorial Desk — verify against the judgment. Source: Supreme Court of India. Corrections